The Port Authority board is set to vote Thursday on a $117.5 million contract to rehabilitate the Trans-Manhattan Expressway after two incidents involving falling debris in May.
The 0.8-mile road runs beneath buildings in Upper Manhattan and connects to the George Washington Bridge’s lower roadway. On May 7, a driver crashed into metal that had fallen from the ceiling. Six days later, officials said a driver was hospitalized after concrete fell onto their car.
The agency made emergency repairs. Port Authority documents say engineers found defects requiring immediate work and an accelerated rehabilitation. The proposed contract would cover concrete, steel joints, beams and walls in a structure that has not had comprehensive rehabilitation since it was built.
If approved, the longer-term work is planned to begin next summer and finish in 2030. Port Authority Executive Director Kathryn Garcia previously attributed the deterioration to repeated freezing and thawing during the winter.





Please note! Comments are published by readers. The opinions expressed may not reflect the position of the editorial team. NYCT is not responsible for the content of readers' opinions and asks authors to observe moral standards, not to incite national or racial hatred, and to avoid rudeness. Think before you speak. You are responsible for your words! By publishing an opinion, you agree to the rules! If this request is ignored, NYCT reserves the right to deprive the user of the ability to leave comments.