Snowy Hydro 2.0 is now projected to cost at least A$22.2bn, with a contingency allowance that could take the total to A$25bn. Snowy Hydro’s latest projections also push full completion and commissioning of the renewable energy project to 2029.
The project in Australia’s Kosciuszko National Park was initially put forward by the Turnbull government in 2017 at a cost of A$2bn. By 2023, its estimated cost had risen to almost A$13bn, with construction then due to finish by the end of 2028.
Snowy Hydro says machine tunnelling is 65% complete and major excavations are nearing completion. Work on the underground power station is under way, with about 5,000 people working on the project.
The Albanese government plans to set out further oversight and financing arrangements in the coming weeks. Another injection of taxpayer funding is expected, while private financing remains a possibility.





Please note! Comments are published by readers. The opinions expressed may not reflect the position of the editorial team. NYCT is not responsible for the content of readers' opinions and asks authors to observe moral standards, not to incite national or racial hatred, and to avoid rudeness. Think before you speak. You are responsible for your words! By publishing an opinion, you agree to the rules! If this request is ignored, NYCT reserves the right to deprive the user of the ability to leave comments.